Timeline


March 2012
20/03/2012 - Official Target Finish Date - 2 Kitchen Bench + Plumber not available
16/03/2012 - Official Target Finish Date - 3 Day Rain Delay
14/03/2012 - Carpet + Outside Clean
13/03/2012 - Official Target Finish Date - 3 Day Rain Delay
12/03/2012 - Inside Clean
09/03/2012 - Water Tank Installed
08/03/2012 - Official Target Finish Date - 1 Day Rain Delay
07/03/2012 - Official Target Finish Date - 1 Day Rain Delay
07/03/2012 - Official Target Finish Date -
07/03/2012 - Tiling Finish
06/03/2012 - Splash Back Installed
06/03/2012 - Official Target Finish Date
01/03/2012 - Tiling Start

February - 2012
28/2/2012 - Internal Plumbing - toilets, taps, kitchen sink shower heads
27/2/2012 - Roof safety barrier comes down
23/2/2012 - Brick Expansion Joints filled
22/2/2012 - Wardrobe carpentry completed
16/2/2012 - Air Conditioning
15/2/2012 - Electrical - Fittings
9-15/2/2012 - Indoor Paint
09/2/2012 - Outdoor Paint + Bag


January - 2012
31/1/2012 - Wet Area tiling finished
24/1/2012 - Wet Area tiles started
19/1/2012 - Decorative trim and columns installed
18/1/2012 - Kitchen and Laundry Cabinets installed
17/1/2012 - Kitchen, Laundry and Bathroom Cabinets arrive
13/1/2012 - Brickies finished the brick work

December - 2011
24/12/2011 - Skirting boards and Windows Frames
21/12/2011 - Front Door, Laundry Door, Garage Door + internal doors - Lockup
17/12/2011 - Cornice Started
16/12/2011 - Wet Areas Started
12/12/2011 - Gyprocking Started

November - 2011
23/11/2011 - Variation 14 - Kitchen Handles (original paperwork had handles on top cupboards no handles on pull out draws - Opps)
22 - 23/11/2011 - Rain Again
21/11/2011 - Roof Complete
16/11/2011 - Roofing Guys on site and safety barriers in place
11/11/2011 - Gutters and Facia Completed, Roof Sheets Delivered
09/11/2011 - Bricks Almost Finished, Brickies out of Face Brick
07/11/2011 - Roofing Attempted Delivery, not enough space on the front of the block

October - 2011
19/10/2011 - More Bricks Delivered, Official Brick Work Start, Plumbing Fixed by now
17/10/2011 - First Course of Bricks
11/10/2011 - First Bricks Delivered
07/10/2011 - Progress Payment 3
02/10/2011 - Plumbing Problems

September - 2011
25/09/2011 - It's Raining on our first walk through, we need a retaining wall, moat all we need are crocodiles
22/09/2011 -  Variation 15 - Remove Provisional Allowance for the water meter and clean fill, official note that front facade is not all bad and render (wasn't carried across from colour selection
21/09/2011 - Checked face brick on front - it turned out that it was missed from Colour selections, emails to CLO
17/09/2011 - Frame Complete
14/09/2011 - Frame Going Up
12/09/2011 - Frame Delivered
08/09/2011 - Variation 14 - Crane Hire to move frame under power lines
08/09/2011 - Shed is started behind us
07/09/2011 - Power Pole Installed
Rain
03/09/2011 - Progress Payment 2
02/09/2011 - Concrete Slab Poor
01/09/2011 - Variation 13 - Extra Concrete for Piering

August - 2011
30/08/2011 - Waffle Pod
29/08/2011 - Official Rain Delay Notice - 1 day
27/08/2011 - Slab Form work - Plumbing Rough In
26/08/2011 - Piering
Rain
20/08/2011 - Portaloo Delivered
19/08/2011 - Variation 12 - Provisional to Move water meter
15/08/2011 - Site Scrape and Peg out
11/08/2011 - Official Construction Start

July - 2011
28/07/2011 - Construction Certificate Issued
27/07/2011 - Demolition Complete - Clearance Certificate
25/07/2011 - House Flattened
22/07/2011 - Variation 11 - note to raise the garage floor (council requirement)
20/07/2011 - Demolition Starts
18/07/2011 - Demolition Fence Goes Up
05/07/2011 - Variation 10 - Electrical Price
05/07/2011 - Variation 9 - (some internal MCD variations take us to 9) This variation takes care of the council requirements including raising the level  of the Aircon, water heater and Rain water tank pads to the flood level height
04/07/2011 - Electrical Appointment

June - 2011
30/06/2011 - Basix and ABSA Certificate finalised
29/06/2011 - Home Owners Warranty Certificate
24/06/2011 - Variation 5 Provide Tender Extension
23/06/2011 - Road Reserve Opening Permit (Paid to Council to allow stormwater to be laid to Street)
22/06/2011 - Progress Payment 1 - Deposit
21/06/2011 - Authority to Commence Construction from Bank
16/06/2011 - Council Approval
15/06/2011 - Council Restarts the Clock
02/06/2011 - Variation 4 SEPP 1 Letter (needed by council to allow building on more than 50% of land)

May - 2011
24/05/2011 - Council Stops the Clock
09/05/2011 - Demolition Approved
04/05/2011 - Plans accepted by Council

April - 2011
27/04/2011 - Tree Pruning / Removal Application Form
20/04/2011 - Variation 3 - Provisional to import Clean Fill, Flood Compliance Survey, Couple of other Council changes
18/04/2011 - Plans submitted to Council
16/04/2011 - Moving Out Today (we thought it would be quick through council)
14/04/2011 - Flood Level Enquiry Received from Council Engineers
13/04/2011 - Demolition Plans Lodged to Council
12/04/2011 - Variation 2 (opp's they only had M class Slab in Contract but we need a P Class)
11/04/2011 - Deposit Paid to Demolition Company
05/04/2011 - Council bounces initial plan lodgement with items to be addressed
01/04/2011 - Contract Signed by all

March - 2011
17/03/2011 - Lawyer Checks over Building Contract
10/03/2011 - Variation 1 (Change Home Theatre to Sliding Doors)
08/03/2011 - Contract

February - 2011
14/02/2011 - Colour Appointment

January - 2011
27/01/2011 - Check out  Bricks at Boral (On the way home)
27/01/2011 - Pre Colour Appointment

December - 2010
16/12/2010 - Consolidated Tender
15/12/2010 - Deposit Variation 2 (updated Quote) - added back alfresco area
03/12/2010 - Deposit Variation 1 (updated Quote) - Aircon and Appliance discount, Country Cottage Facade, Remove LPG for Cook top and oven, change home theatre, add wall to make Spare Room

November - 2010
28/11/2010 - Paid Deposit

September - 2010
Bank Stuff

August - 2010
13/08/2010 - Quotation 1 - 2700 high walls, remove bathtub from ensuite - make laundry bigger, add 3 way bathroom, change vanity's to singles
01/08/2010 - Soil Test and Contour Survey

7/2011 - Realisation that renovations more expensive for what we wanted, Started looking at Display Homes

2/2011 - 8/2011 - Plans and prices for Renovations

Talk to the banks to find a budget for renovations

6/2009 - Contact with Renovation companies

A year or two goes past, should we renovate, move, do we want to live where we are, general procrastination10/11/2011 - Bricks Delivered